ITP has specialized in the management of fast track projects and is capable to deliver PiP systems in a very aggressive planning. For example, here are the key figures of two projects performed for the North Sea :

 

Project

 

FORVIE

 

 

DUNBAR

 

Features

33km  - 34mm heavy wall

22km  - 316 CRA liner

Subassembly type

Double Joint (24.4m/80ft)

Single Joint (12.2m/40ft)

LOI

August 2004

September 2006

Last Joint Fabrication

Mid July 2005

Mid May 2007

Offshore installation

15 August 2005

25 June 2007

Project overall duration

12 months after LOI

10 months after LOI

ITP Management of 2 Fast Track Projects, Forvie and Dunbar 2

 
 

Site map: Home - Corporate - Message from the chairman - History - Strategy - Range of Activities - Mission - Corporate information - QHSE - HSE Commitment - QA/QC - Products - Subsea Production Flowlines - Pipe-in-pipes flowline - ITP Field Joint - Heat-Traced Flowlines - Mc Pipe - Subsea cryogenic pipelines - Onshore pipelines - Engineering services - Design & Engineering - Project Management - Fabrication services and local content - Offshore Assistance - References and publications - News - Track record - Qualifications and Certifications - Flowline - Cryogenics - Glossary - Contact Us - Contact details - Directions - Job opportunities - Web Alliance: Création Référencement - Liens